Laying a deck over an existing patio is attractive because the hard work appears to be done. It can be an excellent solution, and it can also trap a deck in a permanently damp box.
When it works well
The existing surface is sound, stable and free draining.
There is enough height available to build up without causing a problem at the door.
Air can get under and through the new deck.
Where all three are true, building over a patio saves the groundwork entirely and gives a level, stable base that will not settle.
When it does not
Where the slab holds water. A patio with a hollow that puddles becomes a hollow that puddles under a deck, where it never dries and nobody can see it.
Where the paving is loose, cracked, rocking or settling, since the deck simply follows it down.
Where the build up would take the deck within 150mm of the damp proof course.
Where there is no way to ventilate the void.
Checking the existing surface
Walk the whole area and note anything that rocks or sounds hollow.
Pour a bucket of water and watch where it goes. Water should run off, not gather.
Check the fall runs away from the house.
Lift a slab or two where you can, and look at what is beneath. A slab laid on sand with no sub-base will move.
Look for cracking that suggests movement rather than age.
Repair or relay problem areas before building, since it is impossible afterwards.
Height and the damp proof course
This is the constraint that decides most jobs.
The finished deck surface must sit at least 150mm below the damp proof course. Adding 100mm of frame and 25mm of board to an existing patio frequently breaks that.
Measure before committing. Where the height is not available, options are a low profile system, lifting the patio, or building the deck elsewhere.
Never cover an air brick. Build around it or duct through.
Building methods
Adjustable pedestals are the neatest answer. Plastic supports sit on the paving, screw up and down to level the frame, and hold the timber clear of the surface with air all around.
They accommodate the existing fall while giving a level deck, and they need no fixing into the slab.
Timber bearers on pads or shims are the traditional method, with joists carried on battens laid across the paving. Use a damp proof membrane strip or a plastic shim wherever timber would touch the slab.
Fixing directly to the paving is possible with resin anchors into sound slabs, but it gives the least ventilation and is worth avoiding.
In every case, keep timber off the concrete. Timber in permanent contact with a damp slab rots from the underside.
Ventilation
This is the detail that decides how long the deck lasts.
Leave a genuine air gap under the joists, and leave the perimeter open or vented. A deck boxed in on four sides with a fascia is a sealed damp void.
Where a fascia is wanted for appearance, use a slatted or perforated design.
Leave gaps between deck boards as normal so water drains through and air moves upwards.
Make sure water that drains through has somewhere to go across the patio surface and off the edge.
Access
Keep any inspection chamber accessible by building a removable hatch section over it, and mark it so the next owner can find it.
Leave access to gullies and drainage points.
Think about how you would clear leaves and debris from the void, since something will get under there.
The alternative
Where the patio is failing anyway, taking it up and building the deck on proper foundations is frequently less work than it sounds, and the slabs have resale or reuse value.
A deck built on a bad base is a deck built twice.
Where the patio is sound but sits at the wrong level, lifting and relaying it to a better fall is usually quicker than working around the problem with packers.
Either way, decide before ordering timber, since the frame design depends entirely on what it will stand on.