How to Lay a Path on a Sub-Base

How to Lay a Path on a Sub-Base
DIY Guides Editorial 12 August 2026

A path is a narrow patio, and it fails in the same ways: an inadequate sub-base, no edge restraint, and no fall. The narrowness makes the edge problem worse rather than better.

Setting out

Mark the route with pegs and string lines at the finished edges.

Check the width at intervals, since a path that narrows is very visible.

Establish a datum at the high end and mark the finished surface level, then set the fall along the pegs.

Check for services and drains before digging.

Working out the dig depth

Dig depth is calculated down from the finished surface level.

Add together the paving thickness, the bedding layer and the compacted sub-base.

For a typical foot traffic path that is around 22mm of slab, 40mm of bedding and 100mm of sub-base, so around 160mm below finished level.

Set the finished level first, at least 150mm below any damp proof course and slightly below adjoining turf, and work down.

Excavation

Strip turf and remove all topsoil and organic material down to firm subsoil.

Dig at least 100mm wider than the finished path on each side, so the sub-base extends beyond the edging.

Keep the base even and free of soft spots. Dig out any soft area and make it up with compacted Type 1.

On soft or clay ground, lay a geotextile membrane on the formation before the sub-base.

Sub-base

Use MOT Type 1, a graded crushed aggregate that locks together under compaction.

Single sized gravel is not a sub-base and will not consolidate.

For foot traffic on firm ground, 100mm compacted is adequate. On soft ground use 150mm, and more again if a vehicle will ever cross it.

Compact in layers of no more than 75mm to 100mm with a hired plate compactor, running over each layer several times in different directions.

Slightly damp material compacts far better than dry.

The finished surface should ring solid and take no footprints.

Edge restraint

On a narrow path this matters more than on a patio, because a far higher proportion of the construction is at an edge.

Set kerbs, edging blocks or a paving course on a concrete bed and haunch them with concrete up the outside face.

Keep the haunching below the finished soil or turf level so it is hidden.

Set the edging first, to the line and the correct levels, then work the field to it.

Where the path runs against a wall, the wall provides restraint on that side.

Building in the fall

A crossfall of around 1 in 60 to 1 in 80 to one side sheds water.

Set it in the sub-base and carry it through every layer, rather than trying to create it in the bedding.

Never fall a path towards a building.

On a long path, consider where the water collects at the bottom and whether it needs a channel.

Laying slabs

Mix a bedding mortar of around 5 or 6 parts sharp sand to 1 part cement, moist rather than wet.

Spread a full continuous bed around 40mm thick and screed roughly to the fall.

Lay every slab on a full bed, never on dabs. Five blobs of mortar leave voids that collect water, and frost then lifts and cracks the slab.

Wet the back of porous slabs, or prime porcelain with a slurry.

Tap down with a rubber mallet, checking level, fall and flushness with the neighbouring slab.

Use spacers to keep joints consistent.

Laying blocks

Blocks work differently, sitting on a screeded but uncompacted sharp sand laying course around 30mm to 40mm thick.

Lay from the edging, working forward off the laid blocks rather than walking on the screed.

Leave all cutting until the field is complete.

Brush in kiln dried sand and compact with a plate and a rubber sole plate, then brush in more sand and repeat.

Finishing

Leave slabs to set for at least a day before jointing.

Point or joint with a product suited to the paving, in dry mild weather.

Backfill and reinstate turf or borders against the edging.

Check the whole path for anything that rocks or ponds before jointing, since fixing it afterwards means breaking out the joints.