Close board is the fence trades build when the customer wants it to last. It is assembled on site from separate components rather than bought as a unit, and that is exactly why it outlives panel fencing.
What it is made of
Posts, usually 100mm timber or concrete, mortised or slotted to take the rails.
Arris rails, triangular in section, spanning between posts. Two rails for a fence up to about 1.2 metres, three above that.
Feather edge boards, tapered from around 20mm at one edge to 6mm at the other, fixed vertically and overlapped.
A gravel board at the bottom, and usually a capping rail along the top.
Every part is replaceable individually, which is the whole point of the system.
Setting the posts and rails
Set out the whole line with a string before digging, and set posts at the spacing the rails suit, commonly around 1.8 metres between centres.
Concrete posts have cast slots and the rails drop in. Timber posts are either mortised to receive the rail end, or fitted with metal arris rail brackets, which are easier and perfectly sound.
Rails should sit roughly 150mm below the top of the boards and 150mm above the gravel board, with the third rail centred between them where used.
Fix the flat face of the arris rail towards the boards so there is a solid bearing surface to nail into.
Fitting the gravel board
Fit this before any boards, since it sets the bottom line for everything above.
Level it, or step it evenly on a slope, and keep it clear of standing soil where possible.
The feather edge boards sit on top of the gravel board, not on the ground.
Fixing the boards
Work from one end, starting with the thick edge of the first board against the post.
Each subsequent board overlaps the previous one by about 25mm, roughly the width of the thick edge. Less and gaps open as the timber shrinks; more and you waste a significant quantity of boards over a long run.
Use a spacer block cut to the exposed width so every board lands identically, rather than measuring each one.
Fix with two nails per board per rail, driven through the thick edge and through the underlying board's thin edge.
Do not nail through both thicknesses at the thin edge only, which splits the board and prevents natural movement.
Use galvanised or stainless ring shank nails, or exterior grade screws. Plain steel stains the timber and corrodes.
Keeping it plumb
Check every fourth or fifth board with a level. Small errors accumulate, and by the end of a run a consistent lean of two degrees is very visible.
Correct gradually across several boards rather than forcing one board upright.
Keep the tops on a string line, particularly on a raked fence where the line is the only reference.
Capping and finishing
A capping rail along the top protects the end grain of every board from rain, which is where water gets in first.
It stiffens the whole fence considerably and gives a finished appearance.
Fit post caps for the same reason.
Treat every cut end with preservative as you work, not at the end of the job.
Why it lasts
Individual boards can be prised off and replaced in minutes without dismantling anything.
Rails can be replaced with the boards temporarily supported.
There is no rigid frame to rack out of square, and vertical boards shed water rather than holding it on horizontal faces.
Cost and effort
Materials cost noticeably more than waney lap panels and rather more than closeboard panels.
Labour is the real difference. A panel run of ten bays goes up in a day once posts are set; the same run in close board takes considerably longer.
Against that, it is realistic to expect twenty years or more with basic maintenance, which no cheap panel fence will give.