Garden walls crack from below. Almost every leaning, cracked or settled wall was built on a foundation that was too shallow, too narrow, or laid on ground that moves.

What the foundation does

It spreads the weight of the wall over enough ground that the soil can carry it without compressing.

It gets the base of the wall below the depth at which the ground moves with frost and moisture.

It gives a level, straight platform to build from, which makes everything above far easier.

Depth

The controlling factor is ground movement rather than load, since a garden wall is not heavy.

A minimum of 450mm below finished ground level is the usual starting point, and on shrinkable clay it needs to be considerably deeper.

Frost penetrates the top few hundred millimetres of soil, and a foundation within that zone will be lifted and dropped every winter.

Clay shrinks in summer and swells in winter, and that movement extends deeper near trees. On clay within influencing distance of a tree, 900mm or more may be needed, and this is a case for professional advice rather than a rule of thumb.

Dig down to firm, undisturbed subsoil, whatever the depth. Never found on topsoil, fill or made ground.

Width and thickness

A common arrangement for a modest wall is a concrete strip around twice the width of the wall, so a 215mm wall sits on a 450mm strip.

The concrete itself is usually 150mm to 225mm thick.

The wall should sit centrally on the strip, so the load spreads evenly to both sides.

Where piers are used, widen the foundation at the pier positions.

These are sensible figures for a straightforward wall on reasonable ground. Anything tall, retaining, or on poor ground needs designing.

Setting out

Mark the wall line with profiles and string lines rather than pegs alone, so the strings can be removed during digging and put back accurately.

Set out square using the 3 4 5 method where corners are involved, and check diagonals.

Mark the trench width on the ground, allowing for the foundation width rather than the wall width.

Check for buried services before digging.

Digging the trench

Keep the sides vertical and the base level and even.

Remove all loose material from the bottom, since concrete cast on a soft layer settles.

Where the ground falls along the run, step the foundation rather than following the slope. Each step should be a whole number of brick courses, so the brickwork can level out.

Never cast a sloping foundation, which pushes the wall sideways and makes the coursing impossible.

The concrete

A general foundation mix is around 1 part cement to 2 parts sharp sand to 4 parts aggregate, or 1 to 6 all in ballast.

Mix to a workable consistency that holds its shape rather than flowing.

Calculate the volume before ordering: length by width by thickness in metres. A 10 metre run at 450mm wide and 200mm thick is 0.9 cubic metres, which is well over a tonne of material.

Above about half a cubic metre, consider ready mixed concrete.

Levelling and curing

Drive pegs into the trench with their tops at the finished concrete level, checked with a level and a straight edge along the whole run.

Pour and compact with a rake or bar to drive out voids, then screed off to the peg tops.

A tamped or floated finish is fine. It does not need to be smooth, only level.

Leave the concrete at least a few days before building on it, and longer in cold weather.

Cover it in hot or freezing weather, and never pour in frost or when frost is forecast.

Where the top of the foundation sits

Plan the level so the finished concrete is low enough to allow at least two courses of brickwork below ground level, with the damp proof course at least 150mm above the finished ground.

Working that out before digging saves an awkward compromise later.

Trench fill as an alternative

On deeper foundations, filling the whole trench with concrete to just below ground level uses more concrete and far less labour than building brickwork up from a strip.

It is frequently the cheaper option once the depth exceeds about 600mm.