Surface water drainage is the one part of domestic paving that carries a specific planning rule, and it applies to a situation most people do not think of as a planning matter at all.
The front garden rule
In England, laying an impermeable surface of more than five square metres in a front garden requires planning permission, unless the water is dealt with within the property.
The rule was introduced because paved front gardens shed rainwater straight into the road, overwhelming drains and contributing to flash flooding.
There are three compliant routes.
Use a permeable or porous surface so water soaks through where it falls.
Use a solid surface but fall it towards a lawn, border or soakaway inside the boundary.
Apply for planning permission.
Discharging surface water to the highway or into a foul sewer is not acceptable, and connecting surface water to a foul drain is a separate offence that can cause real problems on sale.
What counts as permeable
Gravel and loose aggregate, which drain freely.
Permeable block paving, which uses purpose made blocks with enlarged joints or voids.
Porous asphalt and porous concrete.
Reinforced grass and gravel grids.
Ordinary block paving is not permeable, despite the joints, because the jointing sand and the bedding are designed to shed water rather than admit it.
How permeable paving is built
The construction differs all the way down, and using a permeable surface over a standard sub-base achieves nothing.
Water passes through the surface, into an open graded laying course, then into a storage layer in the sub-base, and finally into the ground or to an outlet.
The sub-base is an open graded aggregate rather than MOT Type 1, because Type 1 contains fines specifically designed to lock together and exclude water.
Typically a clean angular aggregate such as 4/20mm is used, which holds a substantial volume of water in the voids between stones.
Jointing uses a clean angular grit rather than kiln dried sand.
The whole build up is usually deeper than a conventional one, since it has to store water as well as carry load.
Where the water goes
There are three standard approaches, and which applies depends on the ground.
Full infiltration, where all water soaks into the subsoil beneath. This needs free draining ground and a water table well below the construction.
Partial infiltration, where some soaks away and the rest is piped to an outlet.
Tanked, where an impermeable liner holds the water and releases it slowly to a drain, used on clay or where infiltration is unsuitable.
Clay soils drain very slowly, and a full infiltration design on heavy clay simply fills up and overflows.
Soakaways
Where a solid surface is used and water is directed to a soakaway, the soakaway has to be sized and sited properly.
Keep it well away from the house, typically at least five metres, and away from boundaries, trees and other structures.
Test the ground first. A simple percolation test tells you whether the soil will accept water at a useful rate.
A soakaway in clay is frequently just a hole that fills and stays full, which is worse than useless.
Crate systems hold far more water than a rubble filled pit of the same size.
Practical benefits beyond compliance
No standing water and no puddles, since water goes down rather than across.
Less ice in winter, because surface water is not lying about to freeze.
No need to build a fall, which simplifies setting out.
Less pressure on drains during heavy rain.
Maintenance
Permeable surfaces silt up over time as fine material collects in the joints and voids.
Brush and vacuum the surface periodically, and top up jointing grit.
Avoid spreading soil, compost or sand across permeable paving, which blocks it.
Where infiltration slows noticeably, the joints usually need cleaning out and refilling rather than the whole construction replacing.