Removing a Wall: What's Involved

Removing a Wall: What's Involved
DIY Guides Editorial 7 January 2026

Opening up two rooms is one of the most common alterations and one of the few domestic jobs where a mistake can bring part of a building down.

Is it load bearing

The first question, and it must be answered properly rather than guessed.

Indicators that a wall is load bearing:

It runs at right angles to the floor joists above, which you can check by lifting a board or looking from the loft.

There is a wall directly above it on the next floor, or it supports a roof member.

It is thicker than the other internal walls, or is masonry where others are stud.

It continues down through the building and sits over a foundation or a supporting beam in the basement.

It runs in the same direction as the main structural walls of the house.

Indicators that it may not be: a timber stud wall running parallel to the joists, with nothing above it, that stops at the ceiling.

None of these is conclusive on its own. A stud wall can be load bearing, and a masonry wall can be a partition.

If there is any doubt, have a structural engineer confirm it. This is the cheapest part of the job.

What is involved if it is load bearing

A beam is installed to carry the load across the new opening.

The beam bears onto padstones or spreaders at each end, which distribute the load into the remaining masonry.

The masonry below each bearing must be capable of taking the concentrated load, which sometimes means work down to the foundations.

An engineer sizes the beam, specifies the bearings and padstones, and calculates the loads.

Building control approval is required, normally by Full Plans, and the work is inspected.

Temporary support

The most hazardous stage.

Before any of the wall is removed, everything above must be supported.

This is done with adjustable props and needles: horizontal beams passed through holes in the wall, supported on props each side, taking the load while the wall below is removed.

Props must stand on something capable of taking the load, spread with sole plates, and be plumb and correctly tightened.

Floors below may need propping too, so the load passes down to the ground.

The engineer should specify the temporary works. Improvised propping is how collapses happen.

The order of work

Establish whether it is load bearing.

Appoint an engineer and obtain calculations.

Apply to building control.

Check for and isolate services in the wall.

Serve any Party Wall notices required, if the wall is a party wall or excavation is involved.

Erect temporary support.

Remove the wall in stages.

Install the beam, bearings and padstones.

Have it inspected before covering anything.

Fire-protect the beam as specified, which is usually required.

Remove the props only when the beam is bearing correctly.

Make good, and get the completion certificate.

Services

Walls contain cables, pipes, waste runs and sometimes flues.

Isolate and trace everything before starting.

Plan where sockets and switches will go afterwards, since the wall they were on is disappearing.

Non-load-bearing walls

Simpler, and not free of considerations.

Building control may still need to be involved, particularly regarding fire escape, ventilation and room use.

Removing a wall can affect the escape route from a bedroom, and creating an open-plan space through which a stair passes has fire safety implications.

Check with building control rather than assuming a stud wall is nobody's business.

Other things to check

Asbestos in any pre-2000 property.

Whether the wall is a party wall, which brings the Party Wall Act into play.

Whether the property is listed, where internal alterations require consent.

Afterwards

The beam usually needs fire protection, typically boarding, and this is specified rather than optional.

Expect some settlement cracking at the junctions as the structure takes up its new loading, and leave decorating for a few weeks.

Cost

The engineer, the building control fee, the beam and the propping are the fixed costs, and they are a small part of the total.

Most of the expense is in making good: floors, ceilings, plaster, electrics and decoration across two rooms that are now one.

Budget for the whole of that rather than for the beam alone.