Underfloor heating works by warming a large surface gently, so anything that insulates that surface reduces the output. The floor covering is therefore part of the heating system.
The two systems
Electric. Mats or loose cable laid under the floor covering, usually in a layer of adhesive or levelling compound. Straightforward to retrofit, adds little height, and costs more to run.
Water, or wet. Pipes fed from the boiler or heat pump, either in a screed or in a low-profile panel system. Cheaper to run, more disruptive to install, and better suited to whole-house heating.
Electric mats suit a bathroom or a kitchen. Water systems suit new builds, extensions and whole floors.
Tog limits
The key figure for choosing a covering.
The combined thermal resistance of the floor covering and any underlay is commonly required to be below around 2.5 tog, and lower is better.
Above that, the heat cannot get through efficiently, the system runs hotter to compensate and the floor still feels cool.
Manufacturers state tog values. Add the covering and the underlay together.
Thick carpet with a thick underlay very easily exceeds the limit and is the commonest reason underfloor heating disappoints.
Maximum surface temperature
Most flooring manufacturers specify a maximum floor surface temperature, commonly around 27 degrees, and timber floors particularly.
Exceeding it causes shrinkage, gapping, cupping and delamination.
The system must have a floor sensor as well as a room thermostat, set to limit the surface temperature.
Which coverings suit
Tile and stone. The best partner by a distance. Excellent conductors, no temperature restrictions of consequence, and they hold heat.
LVT and vinyl. Good, thin and conductive. Check the product is stated as suitable and observe the temperature limit. Glue-down is generally preferred over click.
Engineered wood. Suitable where stated, and far more stable than solid wood. Gluing down gives the best heat transfer.
Laminate. Usable where the product states it is suitable, with a thin approved underlay.
Solid wood. Generally unsuitable, since it moves too much. Some narrow, quarter-sawn and specifically approved products can be used with care.
Carpet. Possible with a low-tog carpet and a low-tog underlay, and the combination is restrictive.
Build-up and insulation
Insulate below the heating, or a substantial proportion of the heat goes downwards into the slab.
Insulation boards designed for the purpose go under electric mats and under low-profile water systems, and make a large difference to responsiveness.
The damp proof membrane normally sits below the insulation.
Check the whole build-up height against doors and thresholds early.
Commissioning
Not optional, and skipping it damages floors.
Allow adhesives, screed and levelling compound to cure fully before applying any heat. Screed in particular needs a long period.
Bring the system up gradually, typically starting low and increasing by a few degrees per day to maximum, then down again, before laying a timber floor.
Then turn it off or down and lay the floor at normal temperature.
Bring it back up gradually afterwards.
Follow the flooring and heating manufacturers' procedures, since warranties depend on it.
Practical points
Never fix anything through a floor with underfloor heating. Mark the layout and photograph it before covering, and keep the drawing.
Do not lay heating under fitted units, baths or anything permanently in place.
Electrical connection for an electric system in a bathroom is notifiable work.
Rugs and mats over a heated floor create hot spots and can damage the covering.
Running it
Underfloor heating responds slowly, particularly in screed, so it suits being left on at a steady setting rather than switched on and off.
A programmable thermostat that anticipates the warm-up period works better than a simple timer.
Retrofitting
Electric mats are the practical retrofit in a single room, adding only a few millimetres.
Low-profile water systems exist for retrofit and still add height.
In both cases, insulating beneath is what makes the difference between a system that works and one that heats the floor below.
Check the height increase against doors, thresholds and fitted units before ordering anything.
Zoning
Each room or area needs its own thermostat and zone to be controllable, since a single zone across a whole floor heats rooms that do not need it.
Plan the zones and the sensor positions before the floor goes down, since the sensor sits in the floor build-up.
Fit a spare sensor conduit alongside the first, so a failed sensor can be replaced without lifting the floor.