Three prices for the same job frequently vary by a factor of two, and the reason is almost always that the three people are pricing different jobs.
Quote or estimate
The distinction matters and is widely blurred.
A quotation is a fixed price for a defined piece of work. Once accepted it forms a contract, and the price should not change unless the work does.
An estimate is an informed guess and is not binding. The final figure can be higher.
Ask explicitly which you are being given, and get it in writing.
For open-ended work such as repairs where the extent is unknown until opened up, an estimate plus a day rate is reasonable, and the basis should be written down.
Write a specification first
This is what makes quotes comparable, and it is the step most people skip.
Write down exactly what you want done, in as much detail as you can manage.
Specify materials by name and model where you care: which tiles, which paint, which taps, which flooring.
State who is supplying what.
Include the things that are easily assumed: making good, removing waste, protecting floors, reinstating decoration, connecting appliances.
Give every trade the same document. Otherwise you are comparing prices for different work.
How many quotes
Three is the usual advice and remains sensible.
Fewer gives no comparison. Many more wastes everyone's time, and trades talk to each other.
Get them from businesses of a similar size, since a one-man operation and a firm with overheads price differently for good reasons.
Reading a quotation
Is VAT included? This is the single most common cause of a nasty surprise. A price excluding VAT is twenty per cent higher than it appears.
What is specifically excluded? Look for phrases such as subject to survey, excluding making good, excluding electrical work, and price on application.
Are materials included, and to what specification? A provisional sum for tiles means the figure is a placeholder.
Is waste removal included?
Who is responsible for building regulations, applications, fees and certificates?
What is the payment schedule?
Is there a guarantee, what does it cover, and is it insurance backed?
Why the cheapest is cheapest
Sometimes it is a smaller business with lower overheads, which is fine.
Frequently it is one of the following: a thinner specification, cheaper materials, no allowance for waste or making good, no insurance, no intention of finishing at that price, or a misunderstanding of the job.
A price far below the others is information, not a bargain. Go back and ask what it includes.
Equally, the highest is not automatically the best. Ask what it includes that the others do not.
Variations and extras
The commonest source of dispute.
Agree in advance how changes will be priced and authorised.
Anything that changes the work should be confirmed in writing, with a price, before it is done.
Genuine unforeseen problems do arise, particularly in older houses. The test is whether they were reasonably foreseeable at quotation, and whether you were told promptly.
Keep a written record of every variation as it happens, since nobody remembers accurately at the end.
Payment
Never pay the full amount up front.
A deposit for materials on a substantial job is normal and should be proportionate.
Tie payments to completed stages rather than dates.
Hold a final retention until snagging is complete and certificates are handed over.
Pay by traceable means and keep receipts.
Before signing
Check insurance, registration for regulated work and references.
Confirm the start and finish dates in writing.
Remember the fourteen-day cancellation right that generally applies to contracts agreed at your home.
Getting a like-for-like comparison
Where quotes differ widely, put them side by side line by line and identify what each includes.
Go back to each trade with the same questions rather than assuming.
Frequently the gap closes entirely once the specifications match, and the decision then comes down to availability, references and how comfortable you are with the person.
That last point matters more than people expect on a job lasting several weeks in your home.
Timing
Get quotes well before you want the work done, since good trades are booked months ahead.
Be wary of anyone available immediately for substantial work in a busy season.