A whole house is not one project but twenty, and treating it as a single undertaking is how people end up living for years in a building site.
Do nothing for the first month
The strongest advice for anyone who has just moved in.
Live in the house through a season if you can. You will discover where the sun falls, where it is cold, where the damp appears, which rooms you actually use, and where the layout fails.
Plans made before moving in are frequently wrong, and the cost of changing them is highest once work has started.
Use the time to survey rather than to demolish.
Survey what you have
The roof: from outside with binoculars and from inside the loft. Look for daylight, staining, sagging and slipped tiles.
Damp: where, when and what kind. Distinguish condensation from penetrating and rising damp before treating anything.
Drainage and gutters: watch them in heavy rain.
Electrics: the age and type of the consumer unit, and whether there is an installation certificate. An old fuse box with rewireable fuses indicates an installation likely to need attention.
Heating and plumbing: boiler age and service history, radiator condition, pipe material.
Windows and doors: rot, failed double glazing, draughts.
Timber: rot and woodworm in floors, joists and roof.
Insulation: loft depth, wall type, floor.
Asbestos. In anything built or altered before 2000, assume it may be present in textured coatings, ceiling tiles, insulation board, floor tiles, cistern and cement products. Do not disturb anything suspect; have it tested.
The order of major works
Make it watertight and safe first. Roof, gutters, external walls, windows. Then damp and rot, then structural work.
Then services: rewiring, plumbing, heating.
Then plastering, then joinery, then decorating, then flooring.
This holds at whole-house scale exactly as it does room by room.
Phasing over years
Most people do this in stages, and the stages need thinking about.
Do the disruptive whole-house jobs in one go if you possibly can. Rewiring and replumbing involve lifting floors and chasing walls throughout, and doing them room by room means damaging finished rooms later.
If a full rewire is coming, do not decorate first.
Get the roof and damp dealt with regardless of budget, since everything else deteriorates beneath a leak.
Then work room by room, in the order that suits how you live.
Keeping somewhere to live
Establish a clean room and defend it. One room, sealed, where nothing is stored and no work happens.
Keep a working kitchen of some kind, even a temporary one with a sink, a kettle and a microwave.
Never lose the only bathroom without a plan and a date.
Work on one room at a time and finish it, since three half-done rooms is demoralising and one finished room is encouraging.
Which room first
Opinions differ and there are sound arguments.
A bedroom first, so there is somewhere clean to retreat to.
The bathroom early, since living without one is hardest.
The kitchen early if it is unusable, and late if it is merely ugly, since it is the most expensive and disruptive room.
Leave the hall and stairs until last, since everything is carried through them.
Consents
Establish early whether the property is listed or in a conservation area, which changes almost everything.
Check what needs building regulations approval and what needs planning permission before designing around it.
Find out whether permitted development rights have been removed.
The realistic timescale
Whole-house renovation done largely by the owner takes years rather than months.
Plan it that way from the start, in stages that each leave the house better than before, and it is entirely achievable.
Recording what you find
Photograph every wall and floor once it is open, before it is closed up.
Mark on a plan where cables, pipes and structural members run.
Keep the certificates, guarantees and receipts together, since they are needed when you sell.
Budgeting across years
Price the whole house roughly, then price the first stage properly.
Carry a contingency in each stage rather than one for the whole project, since each will need it.
Expect the first stage to overrun most, since that is where the house reveals what it has been hiding.