An hour spent measuring and recording a room before ordering anything prevents the majority of mid-job problems. It is the least interesting part of a project and the highest value.
What you need
- A tape measure, and a laser distance measure if you have one
- A 1200mm spirit level
- A square, and a sliding bevel or angle finder
- A multi-detector
- A torch
- Squared paper, a clipboard and a pencil
- A camera or a phone
Step 1: sketch first, measure second
- Draw the room roughly to shape, not to scale, filling the page
- Include every wall, door, window, alcove, chimney breast and projection
- Mark which way doors open
- Leave plenty of space for figures
- Draw a separate elevation for each wall you are working on
Sketching first forces you to notice every feature before you start measuring.
Step 2: measure the plan
- Measure each wall at floor level and again at about 1.5m. They frequently differ
- Measure the overall length and width, and the individual segments
- Check that the segments add up to the overall. If they do not, measure again
- Measure alcoves at the back, the front and the middle: they are rarely parallel
- Measure diagonally corner to corner, both ways
- Record every figure on the sketch as you take it
Measure the narrowest dimension for anything that must fit into a space, since that is what governs.
Step 3: check square, level and plumb
The step that changes plans.
- Diagonals: equal means square. Unequal tells you by how much it is out
- Corners: measure each with an angle finder or a sliding bevel. Record the actual angles
- Floor: use a long level and a straight edge across the room in both directions. Find the highest point and record the variation
- Walls, plumb: hold a level vertically at several points along each wall. Record any lean
- Walls, flat: hold a long straight edge horizontally against each wall and look for gaps. Record the worst
- Ceiling: measure the height at each corner and the middle
- Openings: measure width and height at three points each
A kitchen where the floor drops 25mm across the room, or a wall that bows 15mm, changes what you order and how you fit it.
Step 4: record the services
Photograph everything before it is covered.
- Sockets, switches and light fittings, with heights from the floor
- Radiators and their pipe positions
- The stopcock and any isolating valves
- Waste pipe positions
- The boiler, its flue and its clearances
- Extractor fans and vents
- Air bricks outside, at low level
- Aerial, data and phone points
- The consumer unit and which circuits serve the room
Scan the walls with a detector and mark cable and pipe runs on the sketch. Note the safe zones from every accessory.
Step 5: record the construction
- Wall type: tap it. Hollow means stud or dot-and-dab; solid means masonry. Measure the thickness at a reveal
- Which walls are structural, as far as you can tell. A wall running at right angles to the joists above is more likely to be loadbearing
- Floor type: suspended timber, which sounds hollow and has air bricks outside, or solid concrete
- Joist direction, from the loft, from below, or from nail lines in boards
- Ceiling type: plasterboard or lath and plaster
- The age of the property, which indicates likely construction
Step 6: look for the problems
The things that change the scope.
- Damp: staining, tide marks, salts, blown plaster, mould, musty smell
- Cracks: photograph and note width and direction. Diagonal cracks near openings deserve attention
- Rot: probe skirtings, window sills and door frames with a bradawl
- Asbestos risk: textured coatings, ceiling tiles, insulation board, floor tiles, cistern, rainwater goods in a pre-2000 building. Do not disturb; get it tested
- Lead paint: assume any pre-1992 paint may contain it
- Old wiring: rubber or fabric insulation, no earth in lighting, round-pin sockets
- Previous unauthorised work, which may need investigating
Step 7: photograph everything
- Wide shots of each wall
- Close-ups of every fitting, junction and defect
- Photographs of anything that will be covered up, with a tape in shot for scale
- Photograph inside a wall or floor before closing it, with measurements marked
- Date the photographs and keep them with the house records
Photographs of concealed services are worth a great deal to whoever works there next, including you.
Step 8: establish a datum
- Find the highest point of the floor
- Mark a level line 1000mm above intended finished floor level, all round the room
- Label it clearly
- Record its height above the existing floor at a fixed point, so it can be re-established
Step 9: the practical constraints
Frequently overlooked until the delivery arrives.
- Can the materials get in? Measure the doorways, the hall, the stair turn and any tight corner
- Will a full sheet of board go up the stairs?
- Where will materials be stored, dry and out of the way?
- Where will waste go, and what will take it?
- Where is the nearest water and power?
- Is there room to work, or does the room need clearing first?
- Where will a skip go, and is a permit needed for the road?
Step 10: write the list
- List the work in the order it must be done
- Note what must be finished before something else can start
- Note what needs a trade, and book them early
- Note what needs notification or approval
- Calculate the quantities, with waste allowances
- Note lead times on anything ordered
- Keep the survey, the sketch and the list together
If it goes wrong
Segments do not add up to the overall: measure again. One figure is wrong.
Room badly out of square: plan to scribe rather than cut to size.
Floor varies significantly: consider levelling it before starting.
Found something unexpected: stop and reassess before ordering.
Materials will not fit through the door: order smaller sheets, or plan a route.