A sagging or bulging ceiling in an older house is usually lath and plaster that has lost its key. It is a safety matter as well as a decorating one.
How lath and plaster works
Thin timber laths are nailed across the joists with narrow gaps between them. Wet plaster is pushed through the gaps and squeezes out above, forming nibs that hook over the laths and hold the ceiling up.
Over a century or more those nibs break off, through vibration, movement, water damage or simple age.
The plaster then rests on the laths with nothing holding it, and it sags.
Step 1: assess it safely
A ceiling that is visibly bulging can come down without warning, and a section of plaster is heavy enough to cause serious injury.
- Do not stand directly underneath while assessing it
- Move furniture and beds out from underneath
- Press very gently on the sagging area with a flat hand. Any springiness or movement means the key has failed
- Tap it: a hollow, drummy sound means it is detached from the laths
- Look for cracks running with the line of the laths
- Check above from the loft or the room above where you can, without putting weight on the ceiling
Where the sag is severe, or plaster is falling, keep the room out of use and get a builder in.
Step 2: find out why
- Water damage: a leak has soaked and weakened the plaster. Fix the leak first
- Age and vibration: the commonest cause, and it affects the whole ceiling rather than one patch
- Loading above: boxes stored in a loft resting on the ceiling rather than the joists
- Structural movement: needs a surveyor
Never store anything on a lath and plaster ceiling from above.
Option 1: re-fix with plaster washers
Suitable where the plaster is sound but detached over a limited area, and there is no crumbling.
What you need: plaster washers, long screws, a detector, a drill and a driver.
- Locate the joists with a detector and confirm with a fine pilot hole
- Check for cables and pipes before drilling
- Position plaster washers over the sagging area, into the joists, at 200 to 300mm centres
- Drill a pilot hole through the plaster
- Drive the screw and washer slowly, drawing the plaster gently back up
- Do not overtighten, which punches the washer through the plaster
- Work gradually across the area, tightening each a little at a time
- Skim over the washers with jointing compound or filler, feathered out
- Sand, prime and paint
This works well on a modest area and is not a fix for a whole ceiling that has failed.
Option 2: overboard it
Plasterboard screwed through into the joists, then skimmed. The usual answer for a whole ceiling.
- Locate and mark every joist, and check for services above
- Use 9.5mm or 12.5mm plasterboard, running at right angles to the joists
- Screws must reach at least 25mm into the joist through the board and the old plaster
- Fix at around 150mm centres
- Stagger the joints
- Tape with scrim and skim
Overboarding does not remove the old ceiling's weight, it adds to it. Where the plaster is crumbling or heavily saturated, this is the wrong choice.
Boards are heavy overhead. Use a board lifter or work with someone else.
Option 3: take it down and reboard
The right answer where the plaster is crumbling, extensively failed, or water damaged.
It is dirty, heavy and disruptive work.
- The room must be emptied and sealed off
- Enormous quantities of dust, and a century of soot and debris from above
- Wear a P3 respirator, eye protection and full covering
- Skip or waste collection required
- It exposes the joists, which is the opportunity to insulate, rewire or fit downlights
Most people have this done rather than doing it themselves.
When to call someone in
- Any ceiling that is visibly bulging or dropping
- Plaster actually falling
- A whole ceiling that sounds hollow throughout
- Any suspicion of structural movement
- Where the ceiling is over a bed or a stairwell
If it goes wrong
Plaster crumbling as you fit washers: it is too far gone. It needs overboarding or replacing.
Washer pulling through: overtightened. Work slowly and stop as it draws up.
Sag returning after overboarding: the old ceiling is still failing behind. It should have come down.
Cracks appearing along joist lines: screws too far apart, or boards not staggered.
Modern plasterboard ceilings
A plasterboard ceiling can sag too, though for different reasons.
- Boards fixed at too wide a spacing, or with nails rather than screws
- Boards too thin for the joist spacing
- Water damage saturating the board
- Insulation or storage loading the ceiling from above
A saturated board will not recover and must be cut out and replaced.
Interim safety
Where a ceiling is sagging and the repair cannot happen immediately, keep the room out of use, particularly for sleeping, and do not load the floor above unnecessarily.
Move anything valuable or breakable out from underneath, and check the area regularly for change.
How long it takes
Fitting plaster washers over a small area is an afternoon plus filling and drying.
Overboarding a room is a day or two plus skimming and four weeks of drying.
Taking a ceiling down and reboarding is the best part of a week including making good.
Add four weeks of drying before painting new plaster, whichever route is taken.
Get quotes for all three routes before deciding, since the difference between overboarding and replacing is frequently smaller than expected once making good is included.