Floor tiles fail for one reason more than any other: the floor moves. Everything below the tile matters more than the tiling itself.

What you need

  • Floor tiles with a suitable slip rating, plus 10 per cent
  • Flexible cement-based adhesive, and a 10 or 12mm notched trowel
  • Tile backer board or 15mm ply, and screws, if overboarding
  • Primer and self-levelling compound if needed
  • Floor tile spacers, 3 to 5mm
  • Tile levelling clips and wedges, for large format
  • Wet cutter
  • Chalk line, long level, tape measure
  • Knee pads, gloves, eye protection

Step 1: check the floor

  1. Walk the floor and feel for any bounce or movement
  2. Check for squeaks and loose boards
  3. Lay a long straight edge across it in several directions and note any dips
  4. On concrete, look for cracks and check for damp

Any deflection will crack the tiles or the grout. A floor that moves under foot must be stiffened before tiling.

Step 2: prepare the substrate

Timber floors: screw down every loose board into the joists. Then overboard with tile backer board or 15mm exterior grade plywood, screwed at 200 to 300mm centres across the whole sheet, staggering the joints. Never tile directly onto floorboards.

Chipboard: overboard as above. Chipboard moves and swells.

Concrete: fill cracks, remove any laitance or old adhesive, and use a self-levelling compound if it is uneven. Check for damp before tiling.

Underfloor heating: turn it off at least 48 hours before tiling and leave it off until the adhesive has cured. Bring it up gradually afterwards. Use flexible adhesive and grout throughout.

Prime the substrate and let it dry.

Step 3: set out

Setting out a floor is about where the cuts fall, and where the eye goes on entering.

  1. Find the centre of the room by measuring between opposite walls and marking the midpoints
  2. Snap chalk lines through both centre points, at right angles
  3. Check the lines are square using a 3-4-5 measurement
  4. Dry lay a row of tiles along each line with spacers, out to the walls
  5. Look at the cut at each edge. Adjust the centre lines by up to half a tile to make the cuts wider and more even
  6. Avoid a narrow sliver anywhere, especially in a doorway

Rooms are rarely square, so work to your chalk lines rather than to the walls.

Step 4: plan your exit

Work out where you will finish before you start.

Tile so you end at the door, working backwards out of the room.

Tiling yourself into a corner is a well-known and entirely avoidable mistake.

Step 5: lay the tiles

  1. Start at the centre, or at the intersection of your lines, and work outwards
  2. Comb adhesive onto the floor with the notched trowel, covering about a square metre
  3. Back-butter each tile with a thin flat layer for solid bed coverage
  4. Press the tile home with a twisting movement
  5. Place spacers at every corner
  6. Check with a level across several tiles as you go
  7. Lift a tile occasionally to confirm at least 95 per cent adhesive coverage

Solid bed fixing is not optional on a floor. Voids under a tile crack it the first time something heavy lands on it.

Step 6: levelling clips

Worth using for large-format tiles.

A clip slides under the edge of two adjacent tiles and a wedge is driven in, pulling their faces flush.

They eliminate lipping, which is very visible on a floor in raking light.

Snap the clips off once the adhesive has set.

Step 7: cuts and edges

Leave the perimeter cuts until the field is laid and set.

Leave a 3 to 5mm gap at every wall for expansion. It is covered by the skirting or a bead of silicone.

Measure each perimeter cut individually.

Step 8: set, then grout

Do not walk on the floor for at least 24 hours, or the time on the bag.

Grout with a flexible floor grout.

Seal the grout once cured.

Silicone the perimeter joint and any doorway threshold, not grout.

Doorways and thresholds

Check the door still clears the new floor before you start. Tile plus adhesive typically adds 12 to 20mm.

Fit a threshold strip where the tiling meets another floor covering.

If it goes wrong

Tiles cracking: deflection in the floor, or voids under the tiles.

Grout cracking in lines: movement in the substrate. It needed overboarding.

Tiles lipping: uneven bed. Use levelling clips and check with a level as you go.

Narrow cut in the doorway: setting out not adjusted. Shift the centre line.

Door will not open: the floor build-up was not allowed for. The door must be trimmed.

Working position

  • Wear knee pads. A floor takes hours on your knees
  • Keep the adhesive bucket beside you and move it as you go
  • Work backwards so you never kneel on a laid tile
  • Keep a bucket of water and a sponge within reach
  • Clear the room completely first, including the doors if they are in the way

How long it takes

An average room takes a day to lay, once the substrate is ready.

Overboarding a timber floor is a day in itself, and self-levelling a concrete floor needs a day of curing.

Then 24 hours before grouting and another 24 before normal use.

Layout patterns

  • Straight or stack bond: simplest, joints line up in both directions, shows any inaccuracy
  • Brick bond: each row offset by half a tile, forgiving of slight size variation
  • Diagonal: makes a small room look larger, generates many more cuts
  • Herringbone: striking, and much more setting out and cutting

Add 15 per cent waste for anything other than straight bond.