With the wall prepared and set out, and a batten fixed, the tiling itself is methodical work.

What you need

  • Tiles, with 10 per cent extra for cuts
  • Adhesive of the correct type, and a mixing bucket and paddle
  • Notched trowel sized to the tile
  • Tile spacers, usually 2 or 3mm for walls
  • Tile cutter, and nibblers or a hole cutter
  • Spirit level, at least 600mm
  • Rubber mallet or a beating block
  • Sponges, buckets, clean water
  • Gloves and eye protection

Step 1: check the setting out

Before opening the adhesive, confirm:

  • The batten is fixed and dead level
  • The vertical starting line is plumb
  • The cuts at each end will be reasonably wide and even
  • Boxes of tiles are opened and mixed together for shade

Step 2: mix the adhesive

Mix to a stiff consistency that holds the notch without slumping.

Let it stand for the stated time, then remix.

Mix only what you can use in the pot life.

Step 3: apply the adhesive

  1. Spread adhesive with the flat edge of the trowel, pressing it into the wall
  2. Comb it through with the notched edge at about 45 degrees, in straight parallel lines
  3. Cover no more than a square metre at a time, or less in a warm room
  4. Keep the notches consistent

Step 4: set the first tile

  1. Place the first tile with its bottom edge resting on the batten and its side edge on the vertical line
  2. Press it home with a slight twisting movement, which collapses the adhesive ribs
  3. Check it with a level in both directions
  4. Do not slide it far, which forces adhesive into the joints

This tile governs everything after it. Take the time to get it exactly right.

Step 5: work outwards

  1. Place the next tile beside the first, with spacers in the joint
  2. Press home with the same twist
  3. Work along the bottom row, then build upwards row by row
  4. Put spacers in every joint, including against the batten
  5. Check with a level every two or three tiles, horizontally and vertically
  6. Correct any drift immediately, while the adhesive is still soft

Use a beating block or a rubber mallet with a piece of timber to tap tiles flush with their neighbours.

Step 6: keep it clean

Wipe adhesive off the face of the tiles as you go, with a damp sponge and clean water.

Dried adhesive on a tile face is difficult to remove and can damage the glaze.

Clean the joints out too. Adhesive filling a joint leaves no room for grout, and it shows through as a different colour.

Rake surplus out of the joints with a spacer or a thin stick before it sets.

Step 7: cuts at the ends

Measure each cut individually rather than assuming they are all the same.

  1. Measure the gap at the top and bottom of the tile position
  2. Deduct the grout joint from each side
  3. Mark and cut the tile
  4. Fit it with the cut edge into the corner, where the next wall or the trim covers it

Step 8: leave it to set

Leave the adhesive at least 24 hours, or the time on the bag for a rapid-set product.

Do not remove the batten early. The tiles will slide.

Step 9: remove the batten and fit the bottom row

  1. Remove the screws and ease the batten away
  2. Clean any adhesive off the wall below
  3. Measure each bottom tile individually, since the floor is not level
  4. Deduct the grout joint at the top and leave a 2 to 3mm gap at the bottom
  5. Cut, fit and press home
  6. Leave the bottom gap to be filled with silicone, not grout

The bottom gap accommodates movement between the wall and the floor or bath.

Step 10: leave before grouting

Leave the whole wall at least 24 hours after the last tile before grouting.

Remove the spacers first if they are the type that sits proud.

If it goes wrong

Tiles sliding down: adhesive too wet, or no batten. Take them off and start again with a stiffer mix.

Rows drifting out of level: not checked frequently enough. Correct while soft.

Adhesive in the joints: rake it out before it sets.

Tiles lipping: uneven adhesive bed, or an uneven wall. Tap flush with a beating block while soft.

Adhesive skinned before tiling: covered too large an area. Scrape off and reapply.

Working around obstacles

Tile the full uncut field of the wall first and leave the cuts and holes until that has set.

Cuts around a shower valve, a window reveal or a socket take far longer per tile, and doing them last means the field tiles are already secure.

How long it takes

An average bathroom wall takes half a day to tile, plus setting out.

A full bathroom is two to three days of tiling, plus a day for grouting and sealing, with drying time between.

Cuts, not whole tiles, take the time.

Working order in a room

  1. The most visible wall first, while you are fresh
  2. Then the remaining walls, working round
  3. Reveals and boxings last
  4. Grout the whole room in one go once everything has set

Grouting the whole room at once gives a consistent colour, since grout shade can vary between batches and mixes.

Leave the last row above a bath or tray until everything else is done, and seal that junction with silicone rather than grout.

Plan the work so the room is not needed while the adhesive cures.