Tiling needs specific tools and most are inexpensive. The mistakes that ruin jobs are consistent, and nearly all happen before the first tile goes on.

The essential kit

  • Notched trowel, sized to the tile: 6mm for small wall tiles, 10 to 12mm for floors
  • Flat trowel for back-buttering
  • Bucket and mixing paddle on a slow-speed drill
  • Tile cutter: manual for ceramic, wet cutter for porcelain and stone
  • Tile nibblers for curves and awkward shapes
  • Tile file or rubbing stone for tidying cut edges
  • Spacers, 2 or 3mm walls, 3 to 5mm floors
  • Spirit level, at least 600mm, and a longer one for floors
  • Timber batten, screws and plugs
  • Grout float, a rubber-faced trowel
  • Sponges and two buckets
  • Skeleton gun for silicone
  • Safety glasses, gloves and knee pads

Worth having

  • Diamond hole cutter for pipes
  • Tile levelling clips and wedges for large format
  • Grout rake or multi-tool for repairs
  • Laser level, which makes setting out much quicker
  • Beating block for tapping tiles flush
  • Grout shaper for a consistent joint profile
  • Suction cups for handling large tiles

The mistakes that cause failures

1. Not priming the substrate. Unprimed plaster sucks the water out of the adhesive before it cures. The tiles come off months later.

2. Tiling onto plasterboard in a shower. Even moisture-resistant board is not waterproof. Use tile backer board and tank it.

3. Assuming grout is waterproof. It is not. The tanking behind the tiles keeps the wall dry.

4. Starting at the floor or the bath. Neither is level. Fix a levelled batten and work off that.

5. Not setting out. A sliver of tile in the most visible corner is permanent, and half an hour with a gauge rod would have prevented it.

6. Ready-mixed adhesive in the wrong place. It is for ceramic wall tiles in dry areas. Not floors, not showers, not porcelain, not large format.

7. No solid bed on a floor. Voids crack tiles. Back-butter and aim for 95 per cent coverage.

8. Grouting movement joints. Bath, tray, worktop, floor junction and internal corners all get silicone. Grout there cracks out within months.

9. Sealing a bath while it is empty. Fill it first, so the joint is at its widest.

10. Too much water when sponging grout off. It washes the grout out and gives patchy colour.

11. Not checking the wall is flat. Large tiles cannot follow a curve. Anything over 3mm in 2m needs correcting.

12. Ignoring the weight limit. Plaster takes about 20kg per square metre, plasterboard about 32. Large porcelain can exceed it.

Order of work

  1. Check and prepare the substrate: flat, sound, primed
  2. Tank any wet area and let it cure
  3. Set out and fix a batten
  4. Fix trim as you tile
  5. Tile the whole field, leaving cuts and holes
  6. Cut and fit the perimeter and around obstacles
  7. Leave 24 hours
  8. Remove the batten and fit the bottom row
  9. Leave 24 hours
  10. Grout
  11. Polish off the haze
  12. Silicone the movement joints
  13. Seal the grout once cured

Keeping it clean

Wipe adhesive off the tile faces as you go. Dried adhesive is very difficult to remove and can damage the glaze.

Rake adhesive out of the joints before it sets, or there is no room for grout.

Change the sponge water frequently. Dirty water spreads a film over everything.

Realistic timings

  • A kitchen splashback: a day, plus grouting the next day
  • A bathroom wall: half a day to a day
  • A full bathroom: two to three days of tiling, plus preparation and grouting
  • A floor: a day for an average room, plus preparation

Preparation typically takes as long as the tiling.

If it goes wrong

Tiles falling off: substrate not primed, or the wrong adhesive.

Grout cracking at corners and edges: those joints needed silicone.

Damp behind tiles in a shower: no tanking.

Patchy grout: inconsistent mixing, or over-sponging.

Sliver of tile in a visible corner: setting out. Nothing fixes it but retiling.

What to buy for a first job

  • Ceramic wall tiles in a medium size, which are the most forgiving
  • A manual score-and-snap cutter
  • Powdered adhesive rather than ready-mixed
  • A 6mm notched trowel and a grout float
  • A 600mm spirit level
  • Plenty of spacers and 10 per cent extra tiles

Start on a splashback or a small area rather than a whole bathroom, and keep the first attempt somewhere it will not be studied daily.

Safety

  • Cutting tile dry produces silica dust. Cut wet, or wear a P3 respirator and work outdoors
  • Wear eye protection whenever cutting or breaking tile
  • Cement-based adhesive and grout are alkaline and irritate skin. Wear gloves
  • Cut tile edges are sharp; file them before handling repeatedly
  • Isolate circuits before working around sockets
  • Check for pipes and cables before drilling into a tiled wall

When to get a tiler in

  • Large-format tiles, which are heavy and unforgiving
  • Natural stone, which is expensive and easily ruined
  • A wet room, where the tanking and falls have to be right
  • A floor with underfloor heating
  • Anywhere the substrate is questionable

A splashback, a bathroom wall or a small floor in ceramic is well within reach for most people.

Hiring rather than buying

Worth hiring for a single job: a wet cutter, a large mixing drill, and a laser level.

Worth buying outright: a manual cutter, a notched trowel, a grout float, spacers and a decent spirit level, all of which are inexpensive and get used again.