Loft insulation is among the most cost-effective improvements to a house. Done without regard to ventilation, it causes condensation, mould and rot in the roof timbers.
The principle
A traditional cold roof works by keeping the loft space cold and ventilated.
- Insulation goes at ceiling level, keeping the heat in the house
- The loft above is cold, and must be ventilated so moisture that gets up there is carried away
- Insulating without ventilating traps moist air against a cold roof, and it condenses
Insulation and ventilation are two halves of the same job.
Step 1: check what you have
- Go up with a torch, and stay on the joists
- Measure the depth of the existing insulation with a ruler pushed down to the ceiling
- Note the type: mineral wool quilt, loose fill, or boards
- Check whether it is evenly laid or has gaps
- Check whether it reaches the eaves, and whether it is blocking them
- Look for damp, staining or mould on the timbers
Step 2: the depth
The current recommendation for mineral wool in a domestic loft is around 270mm.
- Older houses frequently have 100mm or less, and some have none
- Topping up from 100mm to 270mm is a straightforward job
- Beyond about 270mm the additional benefit reduces
- Different materials have different performance, so the depth needed varies with the product
Step 3: laying it
- Lay the first layer between the joists, cut to fit snugly without compressing it
- Lay the second layer at right angles across the joists, covering them
- Crossing the joists is important: it covers the thermal bridge the timber creates
- Butt lengths together with no gaps
- Do not compress it. Compressed insulation does not work
- Work from the far end of the loft back towards the hatch
Step 4: what not to cover
Important, and frequently got wrong.
- Do not insulate underneath a cold water tank. Heat rising from the house below is what stops it freezing. Insulate the sides and the lid instead
- Do not cover recessed downlights unless they are rated for it. They need clearance or a fire-rated cover
- Do not cover electrical cables where it can be avoided; cables buried in insulation carry less current safely
- Do not cover extractor fan ducting; insulate around and over it instead
- Do not block the eaves
- Keep clear of any flue or chimney
Step 5: the eaves
The most common mistake when topping up insulation.
- Insulation pushed hard into the eaves blocks the ventilation path
- The loft then cannot breathe, and condensation forms on the roof underside
- Fit eaves ventilation trays, rigid plastic channels that hold the insulation back and maintain an air gap over it
- A commonly used figure for a standard pitched roof is a continuous 10mm gap at both eaves, or equivalent vents
- Check from outside that soffit vents are present and clear
Insulate right out to the wall plate, but with a tray maintaining the airway above.
Step 6: other ventilation
- Soffit vents: the usual eaves provision
- Ridge vents or a dry ridge system: high-level ventilation, which works well with eaves vents to create airflow
- Tile vents: individual vented tiles set into the slope
- Gable vents: in the gable walls
- A breathable roofing membrane, on a modern roof, allows moisture through and may reduce the ventilation required
Step 7: the loft hatch
A significant weak point.
- Fix a piece of rigid insulation board to the top of the hatch
- Fit a compression draught seal around the frame
- An uninsulated, unsealed hatch loses heat and lets moist air straight into the loft
- Cheap and quick, and it makes a noticeable difference
Step 8: pipes and tanks
- Lag every pipe in the loft, since the space is now colder than before
- Insulate the sides and lid of a cold water tank, not underneath it
- Insulate the expansion tank the same way
- Check pipe insulation is a snug fit with taped joints
A better-insulated loft is a colder loft, so pipes are more likely to freeze. Lagging is not optional after insulating.
Step 9: boarding a loft
Commonly done for storage, and commonly done wrong.
- Boards laid directly on the joists compress the insulation, destroying its performance
- They also stop air moving over it
- The correct approach is a raised boarding system: plastic or timber legs raising the boards above the full insulation depth
- Check the joists can take the load. Ceiling joists in an older house are frequently sized only to hold up the ceiling
- Do not store heavy items on a lath and plaster ceiling
- Boarding a large area may need the joists strengthening, which is a builder's assessment
Safety in the loft
- Stay on the joists. Use a crawl board
- Take a torch and a work light
- Wear gloves, long sleeves and a dust mask when handling mineral wool, which irritates skin and airways
- Wear eye protection
- Watch your head on purlins and roof nails
- Watch for old wiring, and do not disturb it
- Any suspicion of asbestos in old insulation or board: stop and get it tested
If it goes wrong
Condensation after insulating: the eaves are blocked. Fit ventilation trays.
Pipes froze the first winter: the loft is colder now. Lag everything.
Water tank froze: insulation was laid underneath it. Remove it from below the tank.
Insulation compressed under boards: fit a raised boarding system.
Damp patches on the felt: condensation, not a leak. Improve ventilation.
A summary
- Insulation and ventilation are two halves of the same job
- Around 270mm of mineral wool, second layer crossing the joists
- Never insulate underneath a cold water tank
- Fit eaves trays so insulation cannot block the airway
- Insulate and draught-seal the loft hatch
- Lag every pipe, since the loft is now colder