Skimming a whole wall is a skilled job. Skimming a patch of half a square metre is within reach, and it is the only sensible place to learn what plaster does as it sets.
What you need
- Multi-finish or board finish plaster
- A plastering trowel, stainless steel, and a hawk
- A clean bucket and a mixing paddle on a slow drill
- A second bucket of clean water and a brush
- A straight edge or a feather edge
- PVA or an acrylic bonding agent
- A spray bottle of clean water
- Dust sheets, gloves, safety glasses
The trowel matters. A cheap trowel with a rough or pitted blade will drag and tear the surface. A clean, slightly worn-in stainless trowel is far easier.
Step 1: prepare the background
- Clean off all dust, loose material and flaking paint
- Fill any deep hollows with bonding coat first and let it set. Finish plaster is for a thin coat, not for depth
- Control the suction: apply diluted PVA or a bonding agent to porous backgrounds
- Some products want plaster applied while the PVA is tacky; check the container
- Mask off anything you do not want plaster on
Uncontrolled suction is the commonest cause of failure. The background pulls the water out and the plaster goes off before you can work it.
Step 2: mix it
- Put clean water in the bucket first, roughly half the volume of plaster you intend to mix
- Add plaster gradually while mixing with a paddle on a slow speed
- Mix to a smooth consistency like thick custard: it should hold on the trowel without running
- Mix out every lump
- Mix only what you can use in about 20 minutes
Use clean water and a clean bucket. Traces of old plaster accelerate the set dramatically.
Never add water to plaster that has started to go off. It destroys the strength. Discard it, wash the bucket and mix fresh.
Step 3: first coat
- Load the hawk, then take a portion onto the trowel
- Apply from the bottom upwards, with the trowel at a shallow angle
- Spread it thinly, about 2mm, covering the whole area
- Do not try to make it flat yet: the aim is even coverage
- Work quickly and cover the whole patch
Step 4: second coat
Apply once the first has firmed slightly, usually 15 to 20 minutes.
- Apply a second thin coat, again about 2mm
- Now flatten it: work the trowel over the surface to bring it level
- Rule off with a straight edge resting on the sound plaster each side of the patch
- Fill any hollows the straight edge reveals and rule again
Step 5: the trowelling passes
This is what produces a smooth finish, and it is entirely about timing.
- First pass: as the plaster firms, go over the surface with the trowel at a shallow angle to flatten and consolidate it
- Second pass: when it has firmed further and no longer moves under the trowel, go over it again with slightly more pressure. This closes the surface
- Final pass: as it hardens, spray a light mist of water onto the surface and trowel it again. This polishes it
Too early and the plaster moves and ripples. Too late and it will not close and the surface stays open and rough.
Press a finger into it: when it leaves a mark but no plaster comes off, it is ready for the next pass.
The timings depend on the suction, the temperature and the mix. This is why a small patch is the place to learn.
Step 6: clean up
- Wash the trowel, hawk and bucket immediately, before anything sets
- Never wash plaster down a sink; it sets in the trap
- Let the residue settle in a bucket, pour off the water and bin the solids
- A trowel left with plaster on it is difficult to clean and will drag next time
Step 7: drying and painting
New plaster darkens as it sets and lightens as it dries.
- Wait until it is a uniform pale colour with no dark patches
- A small patch may take a few days; a wall takes around four weeks
- Ventilate gently; do not force-dry with heat, which causes cracking
- Mist coat with emulsion thinned 70:30 with water
- Never use PVA as a sealer under emulsion
- Then two full coats
Realistic expectations
A first attempt will not be perfect. It will be flat enough to sand lightly and paint, which is all a patch needs to be.
For a whole wall or a ceiling, a plasterer will do in a day what would take a weekend to do badly.
If it goes wrong
Plaster went off before you finished: mixed too much, suction not controlled, or a dirty bucket. Mix smaller batches.
Surface open and rough: trowelled too late. It can be sanded and skimmed with fine filler.
Ripples and trowel marks: trowelled too early, or too much pressure. Sand and fill.
Plaster dragging and tearing: a dirty or pitted trowel.
Patch cracked: applied too thick, or dried too fast.
Practising first
Plastering is almost entirely about timing, and timing cannot be read about.
- Practise on a spare sheet of plasterboard laid flat or propped up
- Mix a small amount and work through all the stages
- Note how long each stage took in that room, at that temperature
- Do it two or three times before touching a wall that matters
An hour of practice makes a genuine difference to the first real patch.